Hi Ray –
Really appreciate the feedback. So I was looking at the Zimmerman method. It seems that it takes data from yesterday plus today. if that’s the case…
Say it rained a ton yesterday (Monday).
And I have a schedule to run every 3 days (Should be watering on Tuesday, Friday, Monday, Thursday).
So it skips Tuesday because of the rain data. Should I not be able to see the schedule show up on Friday when I look at the Program Preview, since it is scheduled to run and the data that would turn it off hasn’t been computed?